CONTRACTS EXECUTED

CONTRACT EXECUTED – 01

CONTRACT NUMBER CE/042A/2002
WORK DESCRIPTION 132KV & F.O CABLE LAYING WORKS
PLACE OF EXECUTION Karama Colony & Salauhudin Street ( 2 Circuits)
CLIENT M/s Dubai Electricity & Water Authority (DEWA)
MAIN CONTRACTOR M/s ETA Electric Company
SUB-CONTRACTOR M/s Emirates Tower Electrical Contracting (ETEC)

SCOPE OF WORK / WORK CARRIED OUT:

  • vTile removal, removing of wear coarse (Gravel) and excavation in the city area of 6 K.m length for the placement of pre-cast troughs and covers.
  • vCarting or shifting away the sand from the excavated area to the municipality yard without disturbing traffic in the heart of the city.
  • vExcavated trench leveling & compaction for the Field Density Test as per requirement of Client / Consultant.
  • vPlacement of 6 mtr. Length of pre-cast troughs (6 ton) with help of 35 ton crane with all kind of safety as per the requirement of Client / Consultant.
  • vInstallation of road crossing by open-cut method by providing concrete mixture surround the Upvc ducts within certain time limit.
  • vAfter the trough placement soft sand filling up to 100mm thickness for pulling the 132kv as per requirement of Client / Consultant.
  • vPulling of 132kv cable with the help of winch 5 ton or 10 ton M/C cable tension not exceeding 3.5 tons as per requirement of Client / Consultant.
  • v After pulling of 132kv power cable, pulling of F.O cable in the same trench and start filling soft sand up to required level, spread salt water and make it ready for compaction.
  • vFinal backfilling layer by layer (layer of 250mm) up to the ground level with compaction test.

CONTRACT EXECUTED – 02

CONTRACT NUMBER Burj Dubai Infrastructure
WORK DESCRIPTION 132KV & F.O CABLE LAYING WORKS
PLACE OF EXECUTION Bussiness Bay / BurjDubai
CLIENT M/s Emmar Properties
ENGINEER’S M/s Dubai Electricity & Water Authority (DEWA)
MAIN CONTRACTOR M/s ETA Electric Company
SUB-CONTRACTOR M/s Emirates Tower Electrical Contracting (ETEC)

SCOPE OF WORK / WORK CARRIED OUT:

  • vExcavation in the unmade area with approved level profile by Client, for deep of 5 mtrs. For the double circuit to place the pre-cast troughs and covers.
  • vExcavated trench leveling & compaction for the Field Density Test as per requirement of Client / Consultant.
  • vInstallation of road crossing by open-cut method by providing concrete mixture surround the Upvc ducts within certain time limit.
  • vPlacement of 6 mtr. Length of pre-cast troughs (6 ton) with help of 35 ton crane with all kind of safety as per the requirement of Client / Consultant.
  • vAfter the trough placement soft sand filling up to 100mm thickness for pulling the 132kv as per requirement of Client / Consultant.
  • vPulling of 132kv cable with the help of winch 5 ton or 10 ton M/C cable tension not exceeding 3.5 tons as per requirement of Client / Consultant.
  • v After pulling of 132kv power cable, pulling of F.O cable in the same trench and start filling soft sand up to required level, spread salt water and make it ready for compaction.
  • vFinal backfilling layer by layer (layer of 250mm) up to the ground level with compaction test.

CONTRACT EXECUTED – 03

CONTRACT NUMBER DIFC Package – IP 02/02
WORK DESCRIPTION 132KV & F.O CABLE LAYING WORKS
PLACE OF EXECUTION Dubai International Financial Centre ( Behind Sh. Zayed road)
CLIENT M/s Dubai International Financial Centre
ENGINEER’S / Consultant M/s DEWA / M/s Maunsell Consultancy
MAIN CONTRACTOR M/s ETA Electric Company
SUB-CONTRACTOR M/s Emirates Tower Electrical Contracting (ETEC)

SCOPE OF WORK / WORK CARRIED OUT:

  • vExcavation in the Tile & Green area with approved level profile by Client for the single circuit to place the pre-cast troughs and covers
  • vExcavated trench leveling & compaction for the Field Density Test as per requirement of Client / Consultant.
  • vInstallation of road crossing by open-cut method by providing concrete mixture surround the Upvc ducts within certain time limit.
  • vPlacement of 6 mtr. Length of pre-cast troughs (6 ton) with help of 35 ton crane with all kind of safety as per the requirement of Client / Consultant.
  • vAfter the trough placement soft sand filling up to 100mm thickness for pulling the 132kv as per requirement of Client / Consultant.
  • vPulling of 132kv cable with the help of winch 5 ton or 10 ton M/C cable tension not exceeding 3.5 tons as per requirement of Client / Consultant.
  • v After pulling of 132kv power cable, pulling of F.O cable in the same trench and start filling soft sand up to required level, spread salt water and make it ready for compaction.
  • vFinal backfilling layer by layer (layer of 250mm) up to the ground level with compaction test.

CONTRACT EXECUTED – 04

CONTRACT NUMBER DIFC  Package – IP 02/02
WORK DESCRIPTION 11 kv Cable diversion works
PLACE OF EXECUTION Dubai International Financial Centre ( Behind Sh. Zayed road)
CLIENT M/s Dubai International Financial Centre
CONSULTANT M/s Maunsell Consultancy
MAIN CONTRACTOR M/s ETA Electric Company
SUB-CONTRACTOR M/s Emirates Tower Electrical Contracting (ETEC)

SCOPE OF WORK / WORK CARRIED OUT:

  • vManual excavation on the top of existing 11kv live cable approved method of statement by Client for the 17 Nos. of cable for shifting to other corridor.
  • vExcavated trench leveling & compaction for the Field Density Test as per requirement of Client / Consultant.
  • vSupporting of other services like water, sewerage, drainage and irrigation lines with chain pulley and nylon ropes, belts.
  • vEach nos. of cables (Total 17 Nos.) has been given shutdown up to 24 hours., activities like spiking of cable, removing, relocating to the approved corridor by Client / Consultant and jointing .
  • vInstallation of road crossing by open-cut method by providing concrete mixture surround the Upvc ducts within certain time limit.
  • vSoft sand filling up to 100mm thickness for shifting of the 11kv as per requirement of Client / Consultant.
  • vFinal backfilling layer by layer (layer of 250mm) up to the ground level with compaction test.

CONTRACT EXECUTED – 05

CONTRACT NUMBER CE/024C/2004  – Bukidra 400kv s/s to Fahidi 132kv s/s
WORK DESCRIPTION 132KV & F.O CABLE LAYING WORKS
PLACE OF EXECUTION DIHC, Rashid Hospital, Maktoum Bridge & Fahidi (City area)
CLIENT M/s Dubai Electricity & Water Authority (DEWA)
MAIN CONTRACTOR M/s ETA STAR Engineering
SUB-CONTRACTOR M/s Emirates Tower Electrical Contracting (ETEC)

SCOPE OF WORK / WORK CARRIED OUT:

  • vTile removal, removing of wear coarse (Gravel) and Excavation in the city area Route Length of 14 K.m  for the placement of pre-cast troughs and covers.
  • vCarting or shifting away the sand from the excavated area to the municipality yard without disturbing traffic in the heart of the city.
  • vExcavated trench leveling & compaction for the Field Density Test as per requirement of Client / Consultant.
  • vPlacement of 6 mtr. Length of pre-cast troughs (6 ton) with help of 35 ton crane with all kind of safety as per the requirement of Client / Consultant.
  • vInstallation of road crossing by open-cut method by providing concrete mixture surround the Upvc ducts within certain time limit.
  • vAfter the trough placement soft sand filling up to 100mm thickness for pulling the 132kv as per requirement of Client / Consultant.
  • vAfter pulling of 132kv power cable, pulling of F.O cable in the same trench and start filling soft sand up to required level, spread salt water and make it ready for compaction.
  • vFinal backfilling layer by layer (layer of 250mm) up to the ground level with compaction test.

CONTRACT EXECUTED – 06

CONTRACT NUMBER CE/024C/2004  – Oud Metha 132kv s/s to Karama 132kv s/s
WORK DESCRIPTION 132KV & F.O CABLE LAYING WORKS
PLACE OF EXECUTION American Hospital, Maktoum school area & Al karama (city area)
CLIENT M/s Dubai Electricity & Water Authority (DEWA)
MAIN CONTRACTOR M/s ETA STAR Engineering
SUB-CONTRACTOR M/s Emirates Tower Electrical Contracting (ETEC)

SCOPE OF WORK / WORK CARRIED OUT:

  • vTile removal, removing of wear coarse (Gravel) and Excavation in the city area  Route Length of 2.4 K.m  for the placement of pre-cast troughs and covers.
  • vCarting or shifting away the sand from the excavated area to the municipality yard without disturbing traffic in the heart of the city.
  • vExcavated trench leveling & compaction for the Field Density Test as per requirement of Client / Consultant.
  • vPlacement of 6 mtr. Length of pre-cast troughs (6 ton) with help of 35 ton crane with all kind of safety as per the requirement of Client / Consultant.
  • vInstallation of road crossing by open-cut method by providing concrete mixture surround the Upvc ducts within certain time limit.
  • vAfter the trough placement soft sand filling up to 100mm thickness for pulling the 132kv as per requirement of Client / Consultant.
  • vPulling of 132kv cable with the help of winch 5 ton or 10 ton M/C cable tension not exceeding 3.5 tons as per requirement of Client / Consultant.
  • v After pulling of 132kv power cable, pulling of F.O cable in the same trench and start filling soft sand up to required level, spread salt water and make it ready for compaction.
  • vFinal backfilling layer by layer (layer of 250mm) up to the ground level with compaction test.

CONTRACT EXECUTED – 07

CONTRACT NUMBER CE/0409a/2004  – “K”-Stn to IMPZ 132kv s/s
WORK DESCRIPTION 132KV & F.O CABLE LAYING WORKS
PLACE OF EXECUTION Jebel ali, DEWA Tower line area & Emirates road
CLIENT M/s Dubai Electricity & Water Authority (DEWA)
MAIN CONTRACTOR M/s ETA Electric Company
SUB-CONTRACTOR M/s Emirates Tower Electrical Contracting (ETEC)

SCOPE OF WORK / WORK CARRIED OUT:

  • vExcavation in the unmade area with approved level profile by Client, for deep of 5 mtrs. For the double circuit for the Route length of 10 K.mtrs (Hard rock soil) to place the pre-cast troughs and covers.
  • vExcavated trench leveling & compaction for the Field Density Test as per requirement of Client / Consultant.
  • vInstallation of road crossing by open-cut method by providing concrete mixture surround the Upvc ducts within certain time limit.
  • vPlacement of 6 mtr. Length of pre-cast troughs (6 ton) with help of 35 ton crane with all kind of safety as per the requirement of Client / Consultant.
  • vAfter the trough placement soft sand filling up to 100mm thickness for pulling the 132kv as per requirement of Client / Consultant.
  • vPulling of 132kv cable with the help of winch 5 ton or 10 ton M/C cable tension not exceeding 3.5 tons as per requirement of Client / Consultant.
  • v After pulling of 132kv power cable, pulling of F.O cable in the same trench and start filling soft sand up to required level, spread salt water and make it ready for compaction.
  • vFinal backfilling layer by layer (layer of 250mm) up to the existing ground level with compaction test.

CONTRACT EXECUTED – 08

CONTRACT NUMBER CNE/323B/2004
WORK DESCRIPTION 132KV & F.O CABLE LAYING WORKS
PLACE OF EXECUTION Al Awir, “B”- Stn & Creek area, Deria city center area
CLIENT M/s Dubai Electricity & Water Authority (DEWA)
CONSULTANT M/s Mott Mac Donald
MAIN CONTRACTOR M/s ETA STAR INTERNATIONAL
SUB-CONTRACTOR M/s Emirates Tower Electrical Contracting (ETEC)

SCOPE OF WORK / WORK CARRIED OUT:

  • vExcavation in the Inside city & outside city area with approved level profile by Client / Consultant, for the various depth for the multiple circuit Route length of 28 K.mtrs  to place the pre-cast troughs and covers.
  • vExcavated trench leveling & compaction for the Field Density Test as per requirement of Client / Consultant.
  • vInstallation of road crossing by open-cut method by providing concrete mixture surround the Upvc ducts within certain time limit.
  • vPlacement of 6 mtr. Length of pre-cast troughs (6 ton) with help of 35 ton crane with all kind of safety as per the requirement of Client / Consultant.
  • vAfter the trough placement soft sand filling up to 100mm thickness for pulling the 132kv as per requirement of Client / Consultant, Pulling of 132kv cable with the help of winch 5 ton or 10 ton M/C cable tension not exceeding 3.5 tons as per requirement of Client / Consultant.
  • v After pulling of 132kv power cable, pulling of F.O cable in the same trench and start filling soft sand up to required level, spread salt water and make it ready for compaction.
  • vFinal backfilling layer by layer (layer of 250mm) up to the existing ground level with compaction test.

CONTRACT EXECUTED – 09    

CONTRACT NUMBER PO no. 2131200061 & 3441300016
WORK DESCRIPTION 132KV & F.O CABLE LAYING WORKS
PLACE OF EXECUTION MEYDAN, Nad Al shiba area
CLIENT M/s Dubai Electricity & Water Authority (DEWA)
CONSULTANT M/s DEWA
MAIN CONTRACTOR M/s Jazera Emirates Power
SUB-CONTRACTOR M/s Sarmast Khan Electrical Contracting (SKEC)

SCOPE OF WORK / WORK CARRIED OUT:

  • vExcavation in the Inside city & outside city area with approved level profile by Client / Consultant, for the various depth for the multiple circuit Route length of 10K.mtrs  to place the pre-cast troughs and covers.
  • vExcavated trench leveling & compaction for the Field Density Test as per requirement of Client / Consultant.
  • vInstallation of road crossing by open-cut method by providing concrete mixture surround the Upvc ducts within certain time limit.
  • vPlacement of 6 mtr. Length of pre-cast troughs (6 ton) with help of 35 ton crane with all kind of safety as per the requirement of Client / Consultant.
  • vAfter the trough placement soft sand filling up to 100mm thickness for pulling the 132kv as per requirement of Client / Consultant, Pulling of 132kv cable with the help of winch 5 ton or 10 ton M/C cable tension not exceeding 3.5 tons as per requirement of Client / Consultant.
  • v After pulling of 132kv power cable, pulling of F.O cable in the same trench and start filling soft sand up to required level, spread salt water and make it ready for compaction.
  • vFinal backfilling layer by layer (layer of 250mm) up to the existing ground level with compaction test.

EXECUTED CONTRACT VALUES

CONTRACT NO. ROUTE LENGTH (K.Mtrs) List of Companies
CE/042a/2002 6.0 ETA Electric Co.
Burj Dubai Infrastructure – 132kv cables 5.5 ETA Star Engg.
DIFC Package IP 02/02 – 132kv cables 1.5 ETA Star Intl.
DIFC Package IP 02/02 – 11kv cables 25.5 ETA Star Intl.
CE/024c/2004 – Bukidara to Fahidi 14 ETA Star Intl.
CE/024c/2004 – Oud Mehta to Karama 2.4 ETA Star Intl.
CE/409a/2005 – “K”-Stn to IMPZ s/s 20 ETA Star Intl.
CNE/323B/2005 – Major Order 28 ETA Star Intl.
CE/409A/05 18.3 ETA Star Intl.
JT Metro – Dubai Rail Projects Lot Dubai Rail
Al Naboodah MEP LLC (11kv cables) Lot & Misc Al Naboodah engg.
CE/024a/2006 42 ETA Star Intl.
Nakheel – 11kv cable works 220 ETA Star Intl.
CE/455c/2006 6 ETA Star Intl.
CE/455C/2006 6.7 ETA Star Intl.
CE/024A/2006 14.35 ETA Star Intl.
AX201 4.4 ETA PPD
CE/447E & 447D/2007 18 ETA Star Intl.
CE/220F/2007 6 ETA Star Intl.
CE/0497/2009 (city area) 4.2 ETA Star Intl.
CE/0096/2009 23.4 L & T Projects
CE/447E/07 ETA Star Intl.
CE/447E/07 3.9 ETA Star Intl.
CE/468CE/07 & CE/448H/07 12.5 ETA Star Intl.
CE/266/2011 3.98 Jazeera Power
BE SIX Project – LS 3 –  132 Kv 1.5 Jazeera Power
P O No. 3441300016 – Sec – E 10.25 Jazeera Power

Our Contracts

Our Services

  • Electrical Contracting

    Design, Installation of underground up to 400 kV cables laying works for electrical substations. The company excels in Sub-contracting assignments, having served as a sub-contractor for various assignments to such premier organizations as follows as Electro-Mechanical contractors.

  • Technical & Commercial Consultancy

    Technical consultancy & advisory for projects, primarily in the energy sector and those involving manufacture of energy-intensive products. Service include project identification.

  • Trading & Marketing

    Emirates tower group of company is involved in various sales, trading & marketing of specialized electrical, auto spare parts and its accessories.

read more